Table of Contents

 

13.         conclusions.. 13-1

13.1   Introduction. 13-1

13.2   Environmental Outcomes. 13-1

13.3   Noise Impacts. 13-6

13.4   Air Quality Impacts. 13-776

13.5   Water Quality Impacts. 13-7

13.6   Waste Management Implications. 13-7

13.7   Landfill Gas Hazards. 13-887

13.8   Landscape & Visual Impacts. 13-8

13.9   Ecological Impacts. 13-8

13.10 Cultural Heritage Impacts. 13-9

13.11 Hazard to Life. 13-9

13.12 Environmental Monitoring and Audit 13-11

13.13 Overall Conclusion. 13-11

13.14 References. 13-12

 

List of Tables

Table 13‑1       Summary of Key Environmental Outcomes/Benefits

 

 

 


13.                   conclusions

13.1                Introduction

13.1.1            This Report presents an assessment of the potential environmental impacts associated with the construction and operation of the Project.  It can be concluded that the Project is unlikely to breach acceptable environmental standards provided that recommended mitigation measures are adopted.  The principal findings of this Draft EIA Report are presented below.

13.2                Environmental Outcomes

13.2.1            The major sensitive areas within the study area include residential buildings, commercial buildings, hospital, recreational areas and educational institutions.  With the implementation of the proposed mitigation measures, no adverse environmental impacts would be expected at the air, noise and water quality sensitive receivers within the study area during both construction and operational phases.  A summary of the key environmental outcomes arising from the EIA study and benefits of the environmental protection measures recommended are presented in Table 13.1 below.

 

Table 131      Summary of Key Environmental Outcomes/Benefits

Issue

Key Environmental Outcomes/Benefits

The Project

Requirements:

·         Construction of dual one-lane viaducts parallel to the existing TWR between Tuen Mun Road and Hoi Kok Street.

·         Construction of dual-2 lane viaducts parallel to the existing TWR between Hoi Kok Street and Tsuen Tsing Interchange.

·         Widening of the existing at-grade section of TWR from dual 3-lane to dual 5-lane between Tsuen Tsing Interchange and Kwai Tsing Interchange.

·         Modification of the associated existing junctions.

·         Provision of noise mitigation measures.

·         Reprovision/ modification to existing crossing affected.

·         Provision/ reprovision of associated civil, structural, geotechnical, landscaping and associated drainage, traffic installation and lighting works.

 

Benefits:

·         The Project can relieve the traffic congestion at TWR

 

Potential consequences without the Project:

·         Without the Project, it is anticipated that the V/C ratio on TWR will be increased up to 1.2 by 2016 due to the development of north-west New Territories, operation of MTRC west rail and corresponding residential and commercial development, as well as the planned MTR residential development TW5, TW6 and TW7, leading to serious traffic problem.

Development Alternatives

The upgrading of Tsuen Wan Road is the direct method to solve the traffic congestion problem in view of engineering aspects.

In view of environmental aspects, the selected alignment would cause less waste generation, avoid night-time construction and reduce construction period and staging.

Road Traffic Noise Impact

Impact/Problem:

·         Unmitigated noise levels: 35 dB(A) to 82 dB(A)

Environmental benefits of environmental protection measures recommended and environmentally sensitive areas protected:

·         Recommended mitigation measures include: (1) about 1,131m long of 5.5m high cantilevered barrier with 3.5m cantilever inclined at 45o on the Kowloon bound of TWR; (2) about 1,073m long of 5.5m high cantilevered barrier with 3.5m cantilever inclined at 45o on the Tuen Mun bound of TWR; (3) about 279m long of semi-enclosure on the Kowloon bound of TWR; (4) about 189m long of semi-enclosure on the Tuen Mun bound of TWR; (5) about 110m long of full enclosure on Kowloon bound of TWR; (6) about 151m long of full enclosure on Tuen Mun bound of TWR.

·         Mitigated noise levels: 35 dB(A) to 82 dB(A). Noise exceedances at all the representative Noise Sensitive Receivers (NSRs) are due to the non-DP roads. Noise contributions to the overall noise levels at all representative NSRs by the DP roads would be less than 1.0 dB(A) and the DP road noise levels would all be below the relevant noise criteria. No adverse noise impacts arising from the DP roads are predicted at any of the representative NSRs. Implementation of indirect technical remedies are therefore considered not necessary.

·         With the implementation of the direct noise mitigation measures, about 2,721 and 1,264 of the dwellings, classrooms or other noise sensitive units would be benefited and protected, respectively.

Construction Noise Impact

Impact/Problem:

·         Unmitigated noise levels: 40 dB(A) to 94 dB(A), with exceedance of construction noise assessment criteria at 52 representative NSRs.

Environmental benefits of environmental protection measures recommended and environmentally sensitive areas protected:

·         Recommended mitigation measures include: (1) selection and optimization of construction programmes, avoidance of parallel operation of noisy PME, and/or reduction in number and/or the on-time percentage of PME during noise sensitive periods such as school examination period; (2) use of “quiet” PME and working methods; (3) use of temporary at-source noise mitigation measures such as noise barriers, noise enclosures, noise jacket and mufflers; and (4) use of good site practice to limit noise emission from construction site.

·         Mitigated noise levels: 34dB(A) to 81 79 dB(A), 10 existing representative NSRs and 5 planned representative NSRs with residual construction noise impact.

Construction Air Quality Impact

Impact/Problem:

·         Potential air quality impacts are dust nuisance.

Environmental benefits of environmental protection measures recommended and environmentally sensitive areas protected:

·         Mitigation measures: implement the Air Pollution Control (Construction Dust) Regulations and good site practices.

·         No adverse air quality impacts are anticipated.

Operational Air Quality Impact

Impact/Problem:

·         No adverse air quality impacts arising from traffic emission are anticipated at the existing and future Air Sensitive Receivers.

Construction Water Quality Impact

Impact/Problem:

·         General construction activities associated with the construction of the Project could lead to site runoff.

Environmental benefits of environmental protection measures recommended and environmentally sensitive areas protected:

·         All mitigation measures recommended in this EIA Report should be implemented and drainage network should be maintained properly.

·         No unacceptable residual water quality impacts are expected during the construction of the Project.

Operational Water Quality Impact

Impact/Problem:

·         Adverse water quality impacts associated with the operation of the Project are not expected at the water sensitive receivers within the study area.  Thus, there will be no residual impact associated with the operation of the Project.

Waste Management Implications

Impact/Problem:

·         Wastes generated by construction activities: general refuse from the workforce, chemical waste from plant and equipment maintenance, and C&D material from excavation works and the demolition of existing structures.

Environmentally friendly designs recommended:

·         C&D material with suitable characteristics should be reused on-site as far as practicable (approx 24,700 m3).  Surplus material would require disposal to a public fill reception facility (approx. 85,000 m3).

Environmental benefits of environmental protection measures recommended:

·         With the implementation of the recommended mitigation measures and practices for the handling, transportation and disposal of the identified waste arisings, no adverse environmental impacts are expected.

Land Contamination Impact

Impact/Problem:

·         Based on the findings from the desktop studies and site inspection, there are a number of land uses adjacent to TWR that have the potential to cause land contamination. Since the proposed TWR upgrading works are not anticipated to encroach upon these areas, further contaminated land site investigation and assessment is not required.

Landfill Gas Hazard

Impact/Problem:

·         Construction works of the Project are to be carried out in close proximity to Gin Drinker Bay Landfill and within the Consultation Zone. The risks associated with landfill gas during the construction phase are classified as Medium.

·         The risks associated with landfill gas during the operational phase are classified as Low.

Environmental benefits of environmental protection measures recommended and environmentally sensitive areas protected:

·         Landfill gas mitigation measures stated in this EIA Report shall be incorporated into the contract documents and the project proponent shall ensure that all the measures will be fully implemented during the construction stage of the Project in order to further .minimize the risk to the site work force.

·         During the operational phase, the necessary precautions outlines in the Landfill Gas Hazard Assessment Guidance Note (EPD/TR8/97) should be adopted for all maintenance or extension works in order to minimize the risk to the site work force. Requirements should be incorporated into the contract documents if appropriate..

Landscape and Visual Impact

Impact/Problem:

·         Visual effects are particularly prominent along the northern, elevated section where the road is overlooked by a number of residential tower blocks.  The widened road also passes extremely close to a school and through Tsuen Wan Park causing significant visual and landscape effects.

·         Landscape effects along the southern, ground level section, are more pronounced, with the carriageway widening works resulting in the loss of the established belts of casuarina trees on either side of the bypass.

Environmental benefits of environmental protection measures recommended and environmentally sensitive areas protected:

·         Recommended mitigation measures include (1) tree planting proposal; (2) provision of screen walls and planting areas; (3) feature finishes to structures and floor paving; (4) provision of new recreational/ amenity facilities; (5) provision of noise barriers.

·         The implementation of those landscape mitigation works identified will progressively reduce virtually all effects to an acceptable level by Year 10 of Operation.  The only long term, significant residual effect identified is upon the pupils and staff of the Tsuen Wan Salvation Army Nursery School, whose school building and playground will be overshadowed by the proximity and form of the elevated widened road, notwithstanding the provision of a visual/acoustic barrier.

Hazard to Life

Impact/Problem:

·         Road population increases during the operational phase as well as workforce population during the construction of the Project have little effect on the total societal risks in the vicinity of Yau Kam Tau Water Treatment Works (YKTWTW).

Environmental benefits of environmental protection measures recommended and environmentally sensitive areas protected:

·         A number of mitigated measures, such as introduction of no stopping zones and emergency traffic signals on the relevant roads as well as establishing adequate emergency procedures for the Project workforce, are recommended for the project proponent consideration.

Ecological Impact

Impact/Problem:

·         No adverse ecological impact arising from the Project is anticipated.

Cultural Heritage Impact

Impact/Problem:

·         Key sites of cultural heritage interest identified by the Antiquities and Monuments Office occur in Wang Fat Ching She and lie at some distance from the Tsuen Wan Road (about 100 metres). These sites will not be impacted by the proposals either directly, or indirectly.

·         Potential impacts of the Project upon existing grave sites and the archaeology of the surrounding area are considered insignificant.

 

13.3                Noise Impacts

Construction Phase

13.3.1            A Construction Noise Impact Assessment has been undertaken taking into account noise emitted from concurrent projects including Residential Development at TW5, TW 6, TW 7 and Reconstruction and Improvement of Tuen Mun Road. Practical mitigation measures such as the use of QPME employed in the works, temporary noise barriers, noise jackets, mufflers, noise enclosures and limiting the number of plants operated concurrently, are proposed to minimize construction noise impact. Further mitigation including good site practices as mentioned in Section 3.3, as well as proper scheduling to avoid noisy construction during school examinations, can be adopted to further minimize the construction noise impact.

13.3.2            Environmental monitoring and audit should be implemented to ensure the application of necessary noise mitigation measures, construction noise monitoring, as well as to establish an appropriate path for noise complaints handling. EM&A Manual will be prepared in separate with this report.

Operational Phase

13.3.3            In this Traffic Noise Impact Assessment (TNIA), overall noise level for the maximum traffic flow projection of 15 years after the completion of this Project (i.e. Year 2030) has been evaluated.  Determination of the extent of Designated Project with respect to the maximum overall noise level without project at Year 2030 has been conducted.  Detailed studies on the contribution of noise emanated from the proposed new road segments related to the Project has been evaluated.

13.3.4            Direct noise mitigation measures such including cantilevered noise barriers as well as semi and full noise enclosures have been proposed in the noise assessment where necessary, for the compliance of noise standards and requirements stipulated in EIAO-TM and EIAO Guidance Note for TNIA.  With the incorporation of all proposed noise mitigation measures, it is anticipated that no excessive noise would be imposed on any of the identified representative noise sensitive receivers within 300m from the project area, as a result of traffic on the DP roads during the operation phase of the Project. Indirect noise mitigation measures are therefore considered not necessary.

13.4                Air Quality Impacts

13.4.1            Typical construction works and the major dust generating activities have been identified and reviewed. Good site work practices based on the statutory requirements laid down in the Air Pollution Control (Construction Dust) Regulations should be conveyed to site staff to ensure effective implementation of dust control measures during the construction phase. Provided that these recommendations are followed, control on fugitive dust emissions is considered to be adequate.

13.4.2            The operational phase impact due to vehicle emissions has been assessed.  Under the worst case scenario, when the maximum 15-year peak hour traffic occurs, results indicate that the predicted maximum hourly and daily concentrations of NO2 shall comply with the corresponding AQO hourly and daily limits of 300 µg/m3 and 150 µg/m3 respectively at all ASRs.  On the other hand, results of the predicted maximum daily RSP concentration is well below the AQO limit of 180 µg/m3.   In other words, it is anticipated that no potential air quality impact to the ASRs will be resulted associated with the operation phase of this Project, and no mitigation measures for air quality impact during operational phase would be deemed necessary.

13.5                Water Quality Impacts

13.5.1            The Project has the ability to impact on the identified water sensitive receivers, principally through the generation and discharge of silt-laden surface run-off from spoil stockpiling areas and during landscape stripping and embankment reworking. Specific mitigation measures have been specified to control such impacts.

13.5.2            Road run-off from the operational upgraded TWR will contain sediment and organic/inorganic pollutants.  If the measures highlighted in this Report are adopted, and if the drainage network is maintained appropriately, the impacts on the water environment should be minimal.

13.5.3            This water quality impact assessment has identified none of particular insurmountable problems associated with either the road widening construction works or the completed road operation.  A number of mitigation measures have been recommended, which are generally related to good site management.  Given the implementation of these measures, potential impacts associated with the construction and operation of the highway are not considered significant.

13.6                Waste Management Implications

13.6.1            The proposed works are likely to result in the generation of a variety of wastes and require the management of construction materials.  Provided that both waste arising and imported fill are managed using approved methods as described in this Report, no unacceptable adverse environmental impacts are envisaged.

13.6.2            The mitigation measures recommended in Chapter 6 of this EIA Report should be incorporated into a Waste Management Plan and applied through the contract documents to ensure that environmental nuisance does not arise.

13.6.3            There are a number of land uses adjacent to the TWR that, according to Section 3.1 of Annex 19 of the EIAO-TM, have the potential to cause land contamination. The proposed TWR Upgrading works are not anticipated to encroach upon these areas, and therefore further contaminated land site investigation and assessment is not required.

13.7                Landfill Gas Hazards

13.7.1            The LFG Hazard Assessment has been undertaken with respect to the current proposals for the TWR Upgrading works. The assessment has been undertaken in accordance with the EIAO-TM, and the Landfill Gas Hazard Assessment Guidance Note (EPD/TR8/97) issued by EPD.

13.7.2            The risks associated with LFG during the construction phase have been classified as Medium.   Since construction works are to be carried out in close proximity to GDBL and within the CZ, certain mitigation measures are recommended for implementation during the construction phase. The LFG mitigation measures stated in Chapter 7 of this EIA Report shall be incorporated into the contract documents and the project proponent shall ensure that all the measures will be fully implemented during the construction stage of the Project.

13.7.3            The risks associated with LFG during the operation phase have been classified as Low, and any underground utilities formed as part of the road-widening works should be designated as “special routes”, and the necessary precautions outlined in the Landfill Gas Hazard Assessment Guidance Note (EPD/TR8/97) should be adopted for all maintenance or extension works.

13.8                Landscape & Visual Impacts

13.8.1            Visual effects are particularly prominent along the northern, elevated section where the road is overlooked by a number of residential tower blocks.  The widened road also passes extremely close to a school and through Tsuen Wan Park causing significant visual and landscape effects.

13.8.2            Landscape effects along the southern, ground level section, are more pronounced, with the carriageway widening works resulting in the loss of the established belts of casuarina trees on either side of the bypass.

13.8.3            Notwithstanding these significant construction and short term effects the implementation of those landscape mitigation works identified will progressively reduce virtually all effects to an acceptable level by Year 10 of Operation.  The only long term, significant residual effect identified being upon the pupils and staff of the Tsuen Wan Salvation Army School, whose school building and play ground will be overshadowed by the proximity and form of the elevated widened road, notwithstanding the provision of a visual/acoustic barrier.

13.9                Ecological Impacts

13.9.1            Within the project area there is no recognized site of conservation importance, or important habitats, and no species of conservation importance is identified.  Within the project area there are no recognized sites of conservation importance, or important habitats, and no species of conservation importance other than a small planted population of Lagerstroemia Speciosa along a roadside verge.  Some tree felling and transplantation will be required in areas of urban parkland or amenity plantation, but these will be mitigated by compensatory planting. 

13.9.2            With reference to Appendix A of Annex 16 of the EIAO-TM:

·         The project does not lie within any recognized sites of conservation importance (as identified in Note 1 of Appendix A to Annex 16 of the EIAO-TM);

·         The project will not affect any important habitats (as identified in Note 2 of Appendix A to Annex 16 of the EIAO-TM); and

·         The project will not affect habitats supporting significant populations of species of conservation importance (as identified in Note 3 of Appendix A to Annex 16 of the EIAO-TM).  Although a small number of Lagerstroemia Speciosa will require felling, these species are amenity plantation and cannot be considered as a significant population of wild flora.

13.9.3            Having regarded to the conditions above, the ecological impacts would be negligible in this Project.Having regard to the conditions above, it is concluded that a detailed ecological assessment is not required for the project, and that the ecological impacts would be negligible.

13.10            Cultural Heritage Impacts

13.10.1         Key sites of cultural heritage interest identified by the Antiquities and Monuments Office occur in Wang Fat Ching She and lie at some distance from the Tsuen Wan Road (about 100 metres). These sites will not be impacted by the proposals either directly, or indirectly. However, it is recommended that any works leading to changes in the development area near the junction of the Tsuen Wan Road and the Tuen Mun Highway should be noted in order to prevent any damage on the She.

13.10.2         Potential impacts of the upgrading scheme upon existing graves site and the archaeology of the surrounding area are considered insignificant.

13.11            Hazard to Life

13.11.1         This QRA study re-assessed the hazard to life associated with a potential chlorine spill at the Yau Kom Tau Water Treatment Works (YKT WTW) in light of the increased road and workforce population associated with the construction and operational phases of the Tsuen Wan Road Upgrading Project. The study methodology is based on the previous YKT WTW assessment (ERM, 2001) which in turn was very similar to the previous chlorine spill hazard assessment (Scott Wilson, 1998a, b) for Route 8 (formerly Route 16) however the newest projections of the general population in the area have been taken into account. While the ERM (2001) methodology has been carefully re-examined, based on the review of the recent chlorine incidents worldwide, it proved robust and adequate for the present assessment. Thus, numerous revisions introduced to the present methodology relate to the population assumptions.

13.11.2         The QRA shows that the road population increases during the operational phase of the Tsuen Wan Road Upgrading Project as well as the workforce population during the construction phase have little effect on the total societal risks in the vicinity of YKT WTW, as expressed by the total PLL value and the FN curves. While these risks, similar to the ERM (2001) assessment remain within the ALARP region of the HKSPG Risk Guidelines, it should be noted that due to the updated population projections introduced in this study, the general risk levels even for the 2030 project operational phase are slightly lower than those predicted for 2006 in the ERM (2001) assessment.

13.11.3         Since all the mitigation measures at YKT WTW suggested in ERM (2001) to reduce the risk to As Low As Reasonably Practicable levels have already been implemented, no new mitigation measures are recommended in this study. Similarly, since the risk levels to the road and workforce population of Tsuen Wan Road are relatively low due to its significant distance to YKT WTW, and since the risk to this population is dominated by an earthquake event affecting the YKT WTW and the Tsuen Wan Road and subsequent chlorine release at WTW, no mitigation measure that could significantly reduce such risk is considered cost-effective or practicable. Nevertheless a number of measures suggested in Chapter 9 such as introduction of no stopping zones and emergency traffic signals on the relevant roads as well as establishing adequate emergency procedures for the Project workforce are recommended.


13.12            Environmental Monitoring and Audit

13.12.1         Environmental monitoring and audit are recommended for construction dust, noise and water quality, to check compliance with relevant statutory criteria and to ensure the effectiveness of the mitigation measures.  Site inspection and audit are also recommended for waste management and implementation of landscaping during construction.  Details of the recommended mitigation measures, monitoring procedures and locations are presented in a stand-alone Environmental Monitoring and Audit (EM&A) Manual.  This will enable the Contractor to have early warning and provide necessary action to reduce impacts at specific areas if the critical assessment criteria are approached.  The effectiveness of on-site control measures would also be evaluated through a monitoring exercise.  All the recommended mitigation measures will be incorporated in an EM&A programme during implementation.

 

13.13            Overall Conclusion

13.13.1         The findings of this EIA have provided information on the nature and extent of environmental impacts arising from the construction and operation of the Project.  The EIA has, where appropriate, identified mitigation measures to ensure compliance with environmental legislation and standards.

13.13.2         Overall, the EIA for Tsuen Wan Road Bypass, Widening of Tsuen Wan Road between Tsuen Tsing Interchange and Associated Junction Improvement Works has predicted that the Project will generally comply with environmental standards and legislation after the proposed construction and operation stage mitigation measures are implemented.  This EIA has also demonstrated the general acceptability of the residual impacts from the Project and the protection of the population and environmentally sensitive resources.  Environmental monitoring and audit mechanisms have been recommended to verify the effectiveness of recommended mitigation measures.

 


13.14            References

 

Chapter 1 – Introduction

·        Environment Impact Assessment Ordinance (Cap 499).

 

Chapter 2 – Project Description

·        Territorial Development Strategy Review, A Response to Change and Challenges, Final Executive Report (1998), Planning Environment and Lands Bureau.

 

Chapter 3 – Noise Impact

·        Noise Control Ordinance (Cap 400).

·        Traffic Impact Assessment (July 2004), Scott Wilson (HK) Ltd.

·        Calculation of Road Traffic Noise, Department of Transport (UK), 1998.

·        Technical Memoranda on Noise from Percussive Piling.

·        Technical Memoranda on Noise from Construction Work Other Than Percussive Piling.

·        Technical Memorandum on Noise from Construction Work in Designated Areas.

·        Technical Memorandum on Environmental Impact Assessment Process.

 

Chapter 4 – Air Quality Impact

·        Air Pollution Control Ordinance (Cap 311).

·        Technical Memorandum on Environmental Impact Assessment Process.

·        Agreement No. CE82/97 Ref: T524/30.11/N1/0A: Route 10 Environmental Impact Assessment Report.

·        Brode, R.W. (1988): Screening Procedures for Estimating the Air Quality Impact of Stationary Sources. EPA-450/4-88-010, U.S. Environmental Protection Agency, Research Triangle Park, N.C., U.S.A., p 4-17.

 

Chapter 5 – Water Quality Impact

·        Water Pollution Control Ordinance (Cap 358).

·        Technical Memorandum on Standards for Effluents into Drainage and Sewerage Systems, Inland and Coastal Waters.

·        Practice Note for Professional Persons on Construction Site Drainage (1994), Professional Persons Environmental Consultative Committee (ProPECC PN 1/94).

 

Chapter 6 – Waste Management Implications

·        Waste Disposal Ordinance (Cap 354).

·        Land (Miscellaneous Provisions) Ordinance (Cap 28).

·        Public Health and Municipal Services Ordinance (Cap 132).

·        Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment and Lands Branch Government Secretariat.

·        Environmental Guidelines for Planning In Hong Kong (1990), Hong Kong Planning and Standards Guidelines, Hong Kong Government.

·        New Disposal Arrangement for Construction Waste (1992), Environmental Protection Department & Civil Engineering Department.

·        Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), Environmental Protection Department.

·        Works Branch Technical Circular No. 6/92, Fill Management, Hong Kong Government.

·        Works Branch Technical Circular No. 2/93, Public Dumps, Hong Kong Government.

·        Works Branch Technical Circular No. 16/96, Wet Soil in Public Dumps, Hong Kong Government.

·        Works Bureau Technical Circular No. 4/98, Use of public Fill in Reclamation and Earth Filling Projects, Hong Kong Government.

·        Works Bureau Technical Circular No. 5/99, Trip-ticket System for Disposal of Construction and Demolition Material, Hong Kong Government. 

·        Works Bureau Technical Circular No. 25/99, Incorporation of Information on Construction and Demolition Material Management, Hong Kong Government.

·        Monitoring of Solid Wastes in Hong Kong (1997), Environmental Protection Department.

 

Chapter 8 – Landfill Gas HazardLandscape & Visual Impact Assessment

·        EIAO Guidance Note No. 8/2002

·        “Guidelines for Landscape & Visual Impact Assessment”

·        The Landscape institute and Institute of Environmental Assessment 1995.

·        “Guidelines for Landscape and Visual Impact Assessment”

·        The Landscape Institute and Institute of Environmental Management and Assessment – 2nd Edition 2002.

·        Technical Memorandum to the Environmental Impact Assessment Ordinance (EIAO) – Annex 10.

·        Technical Memorandum to the Environmental Impact Assessment Ordinance (EIAO) – Annex 18.

·        Tsuen Wan Road Upgrading – Design Memorandum February 2003.

·        Tsuen Wan Road Upgrading – Investigation, Final Report on Land Resumption of TWTL 307 March 2003.

·        Tsuen Wan Road Upgrading Brief – 2001.

·        Section 16 Application for Development

Tsuen Wan West (TW7)

West Rail, Phase 1

Planning Statement

·        Section 16 Application for Development

Tsuen Wan West Station (TW5)

West Rail, Phase 1

Planning Statement

 

 

 

 

 

Chapter 9 – Hazard to Life

·        Brighton, P W M. (1989a), "Pressures produced by instantaneous chlorine releases inside buildings" UKAEA Report SRD/HSE/R467.

·        Brighton, P W M. (1989b), "Continuous chlorine releases inside buildings: concentrations on emission to atmosphere" UKAEA Report SRD/HSE/R468.

·        Cook, I., N. J. Holloway, W. Nixon and D.W. Phillips (1993), Consultancy on the Environmental Aspects of the Daya Bay Nuclear Power Station for the Government of Hong Kong - Risk Assessment Report.

·        DNV(1997), Quantitative Risk Assessment of the Transport of Chlorine in Hong Kong for Environmental Protection Department.

·        ERM (1997), Reassessment of Chlorine Hazard for Eight Existing Water Treatment Works: Methodology Report, for Water Supplies Department.

·        ERM (1998), Technical Note 1: Application of Wind Tunnel Test Results in Hazard Assessments, Report for Water Supplies Department CE14/96 Reassessment of Chlorine Hazard for Eight Existing Water Treatment Works, for Water Supplies Department.

·        ERM (2001) Reassessment of Chlorine Hazard for Eight Existing Water Treatment Works: Hazard Assessment for Yau Kom Tau Water Treatment Works, for Water Supplies Department.

·        HKPSG, Hong Kong Planning Standards and Guidelines, available at: http://www.pland.gov.hk/tech_doc/hkpsg/english/index.htm

·        HSL (1998a), CFD Modelling of Chlorine Dispersion at Sha Tin WTW, The Health and Safety Laboratory, March 1998.

·        HSL (1998b), CFD Modelling of Chlorine Dispersion at Tai Po Tau WTW, The Health and Safety Laboratory, December 1998.

·        HSE (1998), The Implications of Major Hazard Sites in Close Proximity to Major Transport Routes, Contract Research Report 163/1998 prepared by WS Atkins Safety & Reliability.

·        IChemE (1989), "Chlorine Toxicity Monograph - Updated Version", The Institution of Chemical Engineers.

·        ICI (1995), "Chlorine Handbook", ICI Australia.

·        Lees F P (1996), Loss prevention in the Process Industries, Butterworth Heinemann.

·        Ove Arup (2000), Water Treatment Works Seismic Hazard Assessment - Seismic Assessment of Chlorine Storage Buildings and Chlorine Containers.

·        PlanD(2006) http://www.pland.gov.hk/info_serv/statistics/tables/WGPD_Report_e.pdf

·        Porter (1991), Risk Mitigation in Land Use Planning: Indoor Releases of Toxic Gases, International Conference on Modelling and Mitigating the Consequences of Accidental Releases of Hazardous Materials, 1991.

·        RWDI (1998), Wind Tunnel Study - Reassessment of Chorine Hazard for Yau Kom Tau WTW, Rowan Williams Davies and Irwin Inc., January 1998.

·        Scott Wilson (1998a) Agreement No CE 42/96, Route 16 from West Kowloon to Sha Tin: EIA Study, Final Assessment Report, for Highways Department.

·        Scott Wilson (1998b) Agreement No CE 42/96, Route 16 Alternative Alignment: EIA Study, Final Environmental Assessment Report, for Highways Department.

·        TNO (1992), "Methods for the Determination of Possible Damage to People and Objects Resulting from Releases of Hazardous Materials", CPR 16E, Green Book, 1992.

·        Webber, D M, S J Jones, G A Tickle, and T Wren (1992), UKAEA Report SRD/HSE R587 “ A model of dispersing gas cloud, and the computer implementation DRIFT – II Steady Continuous Releases”

·        Webber (1998), Brief Review of RWDI and DRIFT Results, 16 February 1998.

·        Annexes 4 and 22 of Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM)

 

Chapter 10 – Ecological Impact

·        Annexes 8 and 16 of Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) issued under section 16 of Environmental Impact Assessment Ordinance (Cap. 499)

·        Wild Animals Protection Ordinance (Cap. 170)

·        Forests and Countryside Ordinance (Cap.96)

·        Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586)

·        Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM);

·        Town Planning Ordinance

·        “Guidelines for Implementing the Policy on Off-site Ecological Mitigation Measures” (PELB Technical Circular 1/97, Works Branch Technical Circular 4/97, dated 17 February 1997)

 

Chapter 11 – Cultural Heritage

·        Annexes 10 and 19 of Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM)

·        Antiquities and Monuments Ordinance (Cap 53)